ANALISIS EVALUASI KOORDINASI SISTEM PROTEKSI ARUS LEBIH PADA SWITCHGEAR PLTP PT GEO DIPA ENERGI (PERSERO)
Keywords:
Protection system, protection coordination, short-circuit current, grading time, overcurrent relayAbstract
The electrical protection system in power generation is essential for ensuring reliability and operational continuity. Each protection device has specific settings and operating times, tailored to the protected zones and the types of disturbances that may occur. This research focuses on the analysis and evaluation of protection coordination in the 19 kV switchgear of Geothermal Power Plant Unit 1, operated by PT Geo Dipa Energi (Persero) in Dieng. The objective of this study is to verify the conformity of the existing settings with standards and coordination principles. The analysis is conducted through setting calculations and short-circuit simulations based on data from relay configuration tests under existing conditions. If the existing settings for overcurrent relays do not meet the standards, a resetting process will be carried out using calculations in line with the standards. The resetting of overcurrent relays includes determining pickup current, instantaneous trip settings, and time dial settings to ensure that the grading time between protection system components meets the standards. The results of this study indicate that there are overcurrent relay settings that still do not comply with the standards. After the relay settings have been reset, the analysis shows that the protection system can coordinate effectively in accordance with the standards.
References
Bamatraf, R. S., Pujiantara, M., & Riawan, D. C. (2011). Studi Koordinasi Proteksi Sistem Pembangkit UP Gresik (PLTG dan PLTU). Jurnal Teknik Pomits, 1–7.
Gunawan, A. (2021). Analisis Karakteristik Waktu Kerja Overcurrent dan Ground Fault Relay Bay Kopel Gardu Induk 150 kV Gejayan.
Hadiyanto, M. F. (2018). Analisis dan Evaluasi Sistem Koordinasi Proteksi pada Pembangkit Listrik Tenaga Gas Uap (PLTGU) PT PJB UP Muara Karang Blok I.
Pinastika, S. H. (2017). Analisis dan Evaluasi Sistem Koordinasi Proteksi pada Pembangkit Listrik Tenaga Uap (PLTU) Paiton 1 dan 2.
Saputro, T. D., Hermawan, & Handoko, S. (2015). Evaluasi Setting Relay Proteksi Generator Pada Plan PT. Petrochina International Jabung Ltd. Betara Complex Development Project Menggunakan Simulasi Etap 12.6.0. Transient, 4(4), 1–10.
Triyono, Y., Penangsang, O., & Sjamsjul, A. (2013). Analisis Studi Rele Pengaman (Over Current Relay dan Ground Fault Relay) pada Pemakaian Distribusi Daya Sendiri dari PLTU Rembang. Jurnal Teknik POMITS, 2(2), B159–B164.
Yahdian, U., Juningtyastuti, J., & Karnoto, K. (2017). Analisis Koordinasi Proteksi Generator dan Trafo Generator pada PLTGU Tambak Lorok Blok 2 Menggunakan Software ETAP 12.6.0. Transient, 6(3), 292. https://doi.org/10.14710/transient.6.3.292-300
Yamhiko, F. (2019). Studi Perencanaan Koordinasi Rele OCR dan GFR pada Transformator-4 150/20 kV 60 MVA di Gardu Induk Cawang Lama. IT PLN.