PENERAPAN BIM DALAM PERCEPATAN PEMBANGUNAN ASRAMA MAHASISWA NUSANTARA MANADO
Keywords:
Building information modelling, scheduling, quantity take off, fast trackAbstract
The construction project for the Asrama Mahasiswa Nusantara (AMN) Manado began on December 27, 2023, with a completion time of 247 days. The project is located in Desa Kalasey Dua, Kecamatan Mandolang, Kabupaten Minahasa, Provinsi Sulawesi Utara. The project's owner, PT. Widya Satria, has been tasked with implementing Building Information Modelling (BIM) in the construction process, using BIM 3D, BIM 4D, and BIM 5D. The research methodology used is a literature study and BIM modeling to provide critical work performance data using fast track methods. The results of the analysis are then analyzed using BIM to determine the volume of work, material, and time. BIM implementation using Autodesk Revit and MS-Project helps in reducing the need for resources, such as labor and materials. BIM also facilitates clash detection, allowing the modeling and work schedule to be coordinated and work together. Visual simulations of the project's work progress show that progress is increasing at different stages, with the first stage reaching 3%, the fourth stage reaching 17%, the eighth stage reaching 28%, and the final stage reaching 100%. The project's implementation resulted in a 12.5% increase duration work from the previous 247 days to the new 217 daysReferences
DAFTAR PUSTAKA
APLIKASI BUILDING INFORMATION MODELING (BIM) DALAM PERANCANGAN BANGUNAN GEDUNG , Jurnal Matriks Teknik Sipil DOI: https://doi.org/10.20961/mateksi.v10i3.55999 ISSN: 2354-8630 E-ISSN:2723-4223 Vol 10, No 3 (2022): September e-Jurnal MATRIKS TEKNIK SIPIL/September 2022/264
Berlian C, Adhi R, Hidayat A. 2016 Perbandingan Efisiensi Waktu, Biaya, dan Sumber Daya Manusia Antara Metode Building Information Modelling (BIM) dan Konvensional (Study Kasus: Perencanaan Gedung 20 lantai) Jurnal Karya Teknik Sipil.
Devi Prameswari Ayu Kusuma, Sara Prihantina, Hermawan dan Budi Hasiholan, IMPLEMENTASI PENERAPAN BIM-BASED LCA PADA PEMBANGUNAN GEDUNG, konteks 16, Bali 27 -28 oktober 2022
Eastman, C., Teichloz, P., Sacks, R., & Liston, K. (2008). BIM Handbook: A Guide to Building Information Modelling for Owners, Managers, Designers, Engineers, and Contractors (1st ed.), John Wiley & Sons, Inc.
Januar Pantiga, Anton Soekiman, KAJIAN IMPLEMENTASI BUILDING
Modul 5 pemodelan 3D, 4D, 5D, 6D, dan 7D, serta simulasi dan Level of Development (LoD) Kementerian PUPR 2018.
Nelson, Sekrsari J. 2019. Faktor yang mempengaruhi penerapan Building Information Modelling (BIM) Dalam Tahapan Pra Konstruksi Gedung Bertingkat, Jurnal Mitra Teknik Sipil.
Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Republik Indonesia Nomor 22 / PRT /M/2018 Tentang Bangunan Gedung Negara.
PUPR, T. B. (2018). Panduan Adopsi BIM dalam Organisasi, Pusat Litbang Kebijakan dan Penerapan Teknologi.
Raflis, Yuwono Bambang, Rayshnda R. 2018. Manfaat Penggunaan Building Information Modelling (BIM) pada Proyek Konstruksi sebagai Media Komunikasi Stakeholders, Jurnal Teknik Sipil.
Rina Marina Masri, Yanuarso Afdhauluddin Saputra dan Alya Sekar Hapsari, IMPLEMENTASI BIM PADA PEMBANGUNAN GEDUNG RUMAH SAKIT Iskandar Muda Purwaamijaya, konteks 16, Bali 27 -28 oktober 2022
Kalumata, F., Tanijaya, J., & Bungin, E. R. (2024, July). ANALYSIS OF THE IMPLEMENTATION OF BUILDING INFORMATION MODELING (BIM) IN THE ACCELERATION OF BUILDING CONSTRUCTION MANADO STUDENTS'DORMITORY. In International Conference on Engineering & Appliance Science and International Conference on Social Science (ICEA & ICSS) Proceedings (Vol. 1, No. 1, pp. 9-19).